Beneficiary Country: The Republic of Kenya
Project’s Name: The Rehabilitation and Development of Holla Irrigation project –
(Phase 1).
BADEA’s Financing:
A loan amounting of US $ 5.0 million, to be repaid over a period of 27 years,
including a grace period of 5 years, and an annual interest rate of 1%.
Other Co- financiers:
Government (US $ 1.250 million).
Estimated Project Cost:
The total project cost for first phase of the project is estimated at US $ 6.250
million, out of which US $ 4.078 million is in foreign currencies representing
65.2% of the total cost.
Project Description:
Holla Irrigation Scheme is located on the western bank of the Tana River
District of coast Province. The scheme and the district headquarters are located
at Holla town, about 360 km north of Mombasa and 50 km south of Bura, along the
Malindi to Garissa Road.
The Project consists of:
1. Civil Works:
- Construction of a pontoon based pumping system at the new site of Makere II on
a river terrace of Tana River and providing bank protection over a length of
129m at the intake site to ensure a protected and well defined section for
pumping operations. This involves 500mm thick Galion mattresses filled with hard
core and placed on the sloping banks,
- Construction of two pumping stations and installation of 6 pumps on each of
the pontoons with a capacity ranging from 300 to 370 l/s for each pump. A
generating set and electrical equipment and accessories will be provided near to
the pump station to enable the operators to carry out minor repairs and
maintenance activities,
- Construction of a sedimentation basin at the head of the main canal in order
to mitigate high silt deposits,
- Construction of new 860 m long connecting main canal and rehabilitation of 21
km long existing main canal, rehabilitation / remodeling of canals and drains of
the In- scheme irrigation scheme as well as the rehabilitation / reconstruction
of canal and drain structures,
- Construction of new main canal access road and rehabilitation of existing main
canal access road and roads connecting the villages with the irrigated area.
The total length of the roads are estimated to be between 30 and 35 kilometers,
- Bush clearing and preparation of irrigation field ( leveling , deep plowing),
- Equipping and repair of the project management unit existing offices , staff
housing, workshops, spare parts stores and fuel and oil storage tanks and a
pilot farm of 50 ha,
- Rehabilitation of existing and distribution of the domestic water supply to
five villages.
2- Purchase / Rehabilitation of plant machinery:
In addition to the pumps, generators and control equipment related to the civil
works described above the project will provide plant and machinery and workshop
equipment (Heavy and light plant, Agricultural machinery, tools etc….).
3- Consultancy Services which include:
The review of the engineering designs, the tender documents, assist the PIU to
tendering process and supervision of execution of the project,
On the field training of technicians in charge of the information of the
project.
4- Institutional support:
- Provision of cars and stationary including computers, printers, photocopiers
and office furniture and equipment,
- Provision of Salaries and running cost to the PIU.
Procurement of Goods and Services:
The procurement of goods and services will be as follows:
- Civil works will be procured on the basis of open competitive bidding
restricted to Arab, African or Arab/ African firms,
- Procurement of plant, machinery and tools on the basis of competitive bidding
restricted to local importers and representative dealers,
- Consultancy Services on the basis of a short list limited to qualified Arab,
African or Arab/ African firms according to BADEA’s procedures.
- Procurement of cars, motorcycles, computers and accessories, photocopiers and
office furniture and equipment on the basis of competitive bidding restricted to
local representative dealers and importers.
Project’s Implementation:
Physical implementation of the project is expected to begin during the third
quarter of year 2005 and ends in December 2007.
The National Irrigation Board ( NIB) will be responsible for the implementation
and management of the project. NIB will establish a Project Implementation Unit
(PIU) which will consist of a project manager, an engineer, an accountant and
two drivers. NIB will also establish a steering Committee to oversee the
implementation and management of the project.
Executive Agency:
National Irrigation Board ( NIB)
Nairobi – Kenya
Fax No: 254 2- 722821
Ministry of Finance
Nairobi – Kenya
Fax No: 254-2-316519/316415 |